BLCI’S Updates as of 2:00pm, January 4, 2022
As part of energization process, BLCI experienced system tripped off at around 12:00nn to 3 feeders that had been energized.…
BLCI’S Updates as of 11:30am, January 4, 2022
As of the moment, BLCI facilitates the energization process to essential establishments particularly to the following areas: 10:48am – Feeder…
BLCI’S Updates as of January 3, 2022
Please be informed that BLCI facilitated energization process to essential establishments only with the following details:6:05pm – Feeder Alpha (along…
BLCI’s Update as of December 31, 2021
Bohol Light Company Inc. (BLCI) has three (3) substations with five power transformers. Out of which, only one (1) substation…
To All Our Valued Clients/Customer:
Date: December 29, 2021 Subject: Non-Working Day In the observance of Rizal Day, please be informed that BLCI is CLOSED…
BLCI’s Update as of December 29, 2021
Work Activities: Replacement and Correction of Backbone Lines. For Feeder Hotel – Esabo Road, Tiptip Dist- 100% – Hangos St.,…
BLCI’s Update as of December 28, 2021
Work Activities: Replacement and Correction of Backbone lines. For Feeder Delta 2 – K of C Drive, Poblacion II, 100%…
BLCI’s Update as of December 27, 2021
For Feeder H – Replacement and Correction of Backbone Lines. – Kabangkalan Rd., Cabawan Dist -100% -Tiptip to Manga Rd.…
BLCI’s Update as of December 26, 2021
For Feeder G – Replacement and correction of primary line activities – Casa Road, Tiptip District to Cabawan Road -100%…
BLCI’s Update as of December 25, 2021
For Feeder Delta-2 (along Gallares St. near Lite Port) Replacement of one (1) Primary pole with deformed crossarm 100% For…