BLCI’s Update as of January 21, 2022
Status of the Proposed Schedule of Energization to Primary Lines with Essential Connections
BLCI’s Update as of January 17, 2022
Status of the Proposed Schedule of Energization to Primary Lines with Essential Connections
BLCI’s Update as of 7:30PM of January 13, 2022
Status of the Proposed Schedule of Energization to Primary Lines with Essential Connections.
Notice & Reminder to Our Valued Clients/Customers:
January 8, 2022 BLCI would like to inform you that the temporary sources of our electricity are from Power Barge…
To Our Valued Consumers:
January 8, 2022 Among gihangyo ang tanang mga konsumidor sa Bohol Light Company Inc., nga kung ang inyong mga service…
DUGANG PAHIBALO:
Kami nagapahibalo nga adunay mga team sa BLCI nga nagpahigayon sa pag-inspection sa tagsa-tagsa ka mga connection ngadto sa atong…
BLCI’s Update as of 7:30PM of January 6, 2022
Summary of Energized Feeders: (Backbone Lines with connected essential establishments and with dedicated transformers) Feeder Alpha-1 – along R. Enerio…
DUGANG PAHIBALO As of 8:05pm, Jan. 4, 2022
Sa hinay hinay nakapasiga na si BLCI ngadto sa pipilia ka mga Feeders sama sa Alpha, Delta, Eagle, Foxtrot, ug…
BLCI’S Updates as of 7:00pm, January 4, 2022
Additional energized feeders (Backbone lines only with connected essential establishment) At 6:24pm – Feeder Delta 1- From Dampas Church going…
BLCI’S Updates as of 5:32pm, January 4, 2022
Additional energized feeder (Backbone lines only with connected essential establishment) Part Feeder Golf – along F. Toledo St., H. Zamora…